Internosis - knowledge management,ecommerce and project consulting
*Home>>>Project Manager

Problems with extension - whose fault is this?


My extension started in March. To cut a long story short, it was supposed to take around 10 weeks but has more than doubled despite us moving across the road to allow work to go faster.
Now the works are nearly finished & snagging items are being seen to (for the 5th time!)
In week 6 I was told by my project manager to arrange for my electric meter to be moved. When they came to provide estimate, the builders had cemented over the cable and a 拢650 job became a 拢1750 job!

The electric guys came on Monday to move it (three months later) and spotted that the builders have also built right over my gas service pipe (illegal apparently), my mains water & my telephone line (not ducted).

The project manager is denying any blame as he states he didn't know it was there! The architect hasn't returned my calls but he is friends with the Project manager and apparently he is denying he is at fault for not getting the right plans beforehand.

How can this be our fault!! We weren't advised of anything to do with service cables etc before.

has anyone had something similiar....

That would depend on whether you hired a general contractor who then subcontracted the jobs out, or if you hired everyone yourself piecemeal.

If a general contractor hires all the subs, he is responsible for all phases of the job. And, if someone screws something up, it's up to the subcontractor to make things right. If they don't, the general contractor eats the extra expenses.

If you hired everyone yourself, it's now up to you to get the subcontractor who screwed up to redo the part of the job that caused the problems - and at no extra cost to you (they are under contract to you for a certain scope of work for a given compensation, regardless of what it actually costs them to do the work - including rework to fix a mistake).

If you can't get the subcontractor who's at fault to fix the problem (or compensate you for having the other subcontractor do the extra work), then you have to pay the other subcontractor and go after the subcontractor at fault in court. But, it will be up to you to prove he was at fault.

I was on the jury for a civil trial several years ago, where a general contractor was building a shopping center, including building a new street to access it. Company A (the general contractor) hired Company B to do some sewer line work in the street. And, after the job was completed, a water pipe burst, causing the street to cave in. So, Company A paid for the repairs and then sued Company B for the costs.

Company A contended that the work Company B did to the sewer lines under the water lines caused the damage to the water lines that led to the pipe failure. But, while we in the jury agreed that it was probably Company B's fault, Company A did not fully prove beyond a reasonable doubt that Company B was liable for the street repairs.

Your project manager should definately have considered these things. Its his job to forsee problems like these!

Was there a proper permit for this work? Where is the building inspector,get him out there,request he inspect the progress.

Tags
  Project Control   Project Risk   Project Tools   Project Software   Project Planning   Project Consulting   Project Manager   Project Management   Microsoft Project   Knowledge Solution   Knowledge System   Knowledge Transfer
Related information
  • What to do when another manager (not your boss but still above you) screams at you and is generally evil?

    Take the professional "kiss my a$$" route. When your predecessor delivers unsolicited instruction or advise, simply state in a very polite and professional manner, " That might just ...

  • Looking for a guy called dennis who was at the titanium bar gold coast sat nite aug 2. great bod. great smile

    to get the right answer you must ask the right question, or at least ask a question. so what is your question??

    ...
  • I notice the recent book "Collins Class Submarine Story: Steel, Spies and Spin" lists key people.?

    never heard of this book. Please excuse my ignorance

    ...
  • What was the "final solution to the Jewish question" announced by the Nazis at the wannsee conferece?

    a. b. c. a. a. c.

    ...
  • How should the profits be split on a two way real estate investment?

    Split the profit 50/50. Investor 1 took all the risk, and made it happen from a financial standpoint. Next time agree on how the profit will be split ahead of time, and have a lawyer write up a c...

  • I need help from a Computer and Information Systems Manager. Can anyone please help with my assignment?

    programming and project help- ...

  • To Move or Not to Move...

    Ok...well...I actually took the time to read all that. Perhaps because I've been there, done that. This calls for some real 'soul searching'. You have to seat down and think all this...

  • Who can tell me something about money managers or portfolio mangers?

    Money managers manage stocks, bonds, and other financial assets for individuals, businesses, and governments. While all money managers have their own unique styles and techniques, the key to being ...

  •  

    Categories--Copyright/IP Policy--Contact Webmaster